All-Day Closure on November 17th
< All-Day Closure on November 15th | Building the New Bridge |
Cutting and Capping the Piles >
November 17th was another
all-day bridge closure day. The two concrete bridge sections adjacent to the west
abutment were removed to allow the placement of the final two piles. After the last pile was
driven, the deck slabs were re-installed. This bridge closure was
also shorter than anticipated, and the bridge was re-opened at 1:30 pm.

West abutment with the 2 deck slabs removed

Center pile of new bent #1 being vibrated in with the north pile of bent #1
visible

Driving the last pile of the new bridge, the north pile of bent #1

Bridge concrete sections being reinstalled over the new bridge piles
With all of the piles driven, the American Construction Company Tugboat
Chelan,
140 Ton
Floating Crane D.B. Palouse, and Flat Barge
Skagit
were no longer needed and were returned to the company's Tacoma headquarters.
Click
here to see a short time-lapse
video of the pile driving taken from our webcam.