Installing the Piles
< Piles and
Piers | Building the New Bridge |
All-Day Closure on November 15th >
On Friday morning, October
28th, 2011, the American Construction Company Tugboat
Chelan,
140 Ton
Floating Crane D.B. Palouse, and Flat Barge
Skagit
pulled through the passage between Stretch Island and Treasure Island and
started work later that morning.

American Construction
Company tug, barge, and crane arriving at Treasure Island
The pile was vibrated
in to within 8 feet of the final design depth by the hydraulically powered
vibrator; the diesel pile driver was then used to drive the pile
to its design depth of 25 feet. The foam around the pile, as seen in the second
picture below, is actually bubbles being
generated by a bubble barrier, which deadens the sound of the pile driving to
prevent damage to any native sea life.

Vibrator being used to set the pile

Diesel-powered pile driver with bubble barrier around pile
As the piles were being driven to their final depth,
the Exeltech engineer counted the number of blows per foot
required to get the pile to its final depth. The engineer did this for
each pile. The "blows per foot" count is critical in ensuring
that the pile-bearing capacity is achieved for both load and seismic design
capacity.

Exeltech engineer (in yellow jacket) counting and documenting the number of
blows per foot
< Piles and
Piers | Building the New Bridge |
All-Day Closure on November 15th >