Excavating the West Abutment
< Snow Day | Building the New Bridge
| Pouring Piers 11, 12, and 13
>
On Monday, January 23rd work on the mainland side
abutment (Pier 1) was started. Before the excavation for the abutment could
begin, the detour driving lane had to be shored up. To do this, a 15-foot-long
wall of steel sheet piles was driven into the ground along the south side of the
detour driving lane. A mobile crane and a hydraulically powered vibrator were
brought in to drive, or vibrate, the sections of the sheet piles into
place. This vibrator was a smaller version of the one used to vibrate the piles
in. After the steel retainer wall was in, the Pier 1 location had been partially
excavated by the end of the week.

Steel sheet piles being driven adjacent to detour
lane

Steel sheet pile wall installed

Excavation of Pier 1 location with a section of
the old abutment removed