Cutting and Capping the Piles

< All-Day Closure on November 17th | Building the New Bridge | Switching Over to the Detour >

On Monday, November 21, 2011, a second barge and crane were brought out to continue the bridge construction. They were the American Construction Company Tugboat Tulalip, 32.25 Ton Floating Crane D.B. Snohomish, and Flat Barge Everett.

The Barge Everett brought with it the materials necessary to continue with the construction of the bridge, which included gravel for inside the piles, the coated rebar cages, reinforcing steel, and wooden form material. 

American Construction has started on the pile caps and estimate they will take 5 weeks to build. Their schedule is to pour 3 pile caps per week.   

At each of the new bent locations, American Construction workers weld supports to each pile to support aluminum scaffolding on the east and west side of the piles. The aluminum scaffolding is used by the crew to cut the excess off the tops of the piles. The tops of the piles are then cleaned up and repainted.

The inside of the piles are pumped of any excess water and filled with gravel up to 2 feet below the bottom of the rebar cage, which extends 10 feet into the pile. 

"I" beam stubs are welded to the east and west sides of the piles to support the steel "I" beams that run north and south, which form the main support for the base of the pile cap concrete form.

Wooden plates are attached to the top of the steel "I" beam and will attach to the plywood base of the pile cap concrete form. The wooden plywood platform is larger than the pile cap will be and serves as a work platform also. The piles and formwork for the pile caps are established both horizontally and vertically using a survey transit and are marked on the plywood base to establish the exact location of the pile cap. The platform is built to support the concrete forms, reinforcing steel, and prefabbed rebar cages installed into the steel piles. The design of our bridge requires the pile cap to sit on top of the pile. For this reason, a sheet metal shroud is temporarily attached to each pile top to give this separation.

Once American Construction finishes the base platform, they call in the "Ironworkers" to place and tie the reinforcing steel that will be cast inside of the concrete pile cap and attaches to the rebar cages that are inserted into the piles.

Removing excess water from the south pile of bent #14

Aluminum scaffolding used to access the tops of the piles

Excess steel pile cut and ready for the crane to remove

Pile cap with I-beam stubs welded on and top repainted

North and south I-beams with wooden plates attached

Sheet metal shroud around top of pile cap

Wooden sub structure of the pile cap base

Up-close picture of the pile, shroud, substructure, and plywood pile cap base

Pile cap base and work platform

Pile cap base with the pile cap form base located and the rebar cages inserted into steel pile

Ready for the Ironworkers!

On Monday, December 12th, the ironworkers started building the rebar framework which will be inside each of the new pile caps. The rebar cages protruding from the steel piles are connected to this framework. American Construction anticipates completing 3 pile caps per week. This schedule will allow them to pour concrete once a week for the next 5 weeks. This means at least one 4- to 5-hour closure of the bridge per week.

Ironworkers starting on a pile cap

Ironworkers tying it all together

Ironworkers building one of the pile cap coated rebar structures

Upper supports added to tie the precast slabs together that go between pile caps

Pile cap partially formed for concrete

< All-Day Closure on November 17th | Building the New Bridge | Switching Over to the Detour >

 

Contact: TICC Board | Webmaster